# Can a final certificate make a low final account binding?

Yes, if a conclusive evidence clause makes the final certificate binding on the matters it names and nobody challenges it in time.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

The final certificate is the last certificate on a job, and under JCT it is called the Final Certificate. A conclusive evidence clause is the term that turns it into proof of the matters it names, such as the final value. So a low figure can stand even if you never agreed it.

What becomes binding, when the clock starts, how long you have and what counts as a challenge all depend on the actual clause and the facts. A letter objecting to the certificate may not protect you, and nor may ongoing negotiations. Send the certificate, the contract and the relevant correspondence to your solicitor straight away. Do not start some quick, generic proceeding on the assumption that it stops the clock.

For the routine on the day a certificate arrives, see [diarise the final certificate's conclusive evidence period](<https://www.quantsurv.com/final-accounts/tips/conclusive-evidence-clauses>).

For a supported account review, with potential challenge deadlines flagged for prompt verification by your solicitor, see our [Final account dispute assessment and response](<https://www.quantsurv.com/claims#client-types>) service.