# Can a final account dispute go to adjudication?

Yes, where the Construction Act covers your contract, a final account dispute can go to adjudication at any time.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

Yes, where the Housing Grants, Construction and Regeneration Act 1996 covers your contract, a final account dispute can go to adjudication at any time. The right comes from [section 108 of the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/section/108>), subject to your contract and the law that applies. You can refer the whole account or a single head.

Before you choose, check the contract, whether the Act covers it and whether an adjudicator can decide the point. Check the notice history, the procedure that applies and any finality or settlement term already in place.

A whole account brings many heads and many questions of evidence. A single head is narrower and easier to manage. Which to refer is your choice, made on the advice of whoever will run the adjudication, not a fixed rule. Pin down the dispute and your evidence with them first, and do not assume a timetable for getting paid.

To have the money side of an adjudication on a deadlocked head built for whoever conducts it, see our [Final account dispute assessment and response](<https://www.quantsurv.com/claims#client-types>) service.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 108 (Right to refer disputes to adjudication)](<https://www.legislation.gov.uk/ukpga/1996/53/section/108>). legislation.gov.uk.

[Browse completion and contract endings in the Library](<https://www.quantsurv.com/library#topic-completion>)

[Browse the Library](<https://www.quantsurv.com/library>)