# Write the site diary the same day, every day

Write the record while events are fresh. Date later corrections honestly and distinguish what you saw from what someone else reported.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

A contemporaneous diary normally gives a clearer record than a later reconstruction because details and supporting material are still available. Keep the routine on ordinary days too. A late record is not automatically worthless: date it honestly, name its sources and check it against other evidence. Preserve original entries and make corrections transparently.

## How do I do it?

1.  Set a time at the end of every shift for the diary, and treat it as part of the day's work, not an extra.
2.  Put the date and the writer's initials on each entry, and if the diary is on an app, leave the timestamps alone.
3.  Write the weather, the labour on site and the areas worked on a quiet day, so the run of dates is unbroken.
4.  Say so in the entry if it is late: written on Thursday for Tuesday, from memory, and why.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) assigns responsibility for contemporaneous site records and checks that the routine is being followed.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)