# Source every rate on the page

Show where each rate comes from and why it applies. Separate actual cost, agreed rates and estimates so the calculation can be checked.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

The other party's surveyor reads your claim looking for a line they can strike without effort. A rate with no source is that line. It takes them one sentence to say not accepted, and you a week to find the source they could have read on the page. Every rate near it is then read with the same suspicion. Rates are also where claims get quietly inflated, so one bare rate suggests the rest were picked, not worked out. A source beside the figure turns this round: now they have to explain why the schedule, the invoice or the published data is wrong.

## How do I do it?

1.  Add a source column to every rate schedule and build-up, and fill it in as each rate goes in, not afterwards.
2.  Name the source exactly: the contract schedule item, the invoice number and date, the published data and its edition, or the payroll period.
3.  Show the build-up on the same sheet for any rate you have built up, with each part sourced in turn.
4.  Check the column for blanks before the claim goes out, and either source each rate or mark it as an estimate.

Our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) connects each rate to its source and explains adjustments from recorded cost to the amount claimed.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)