# Name people, places and hours, not conclusions

Record the event, location, people and effect you observed. Specific facts are easier to assess than a general statement that the job was disrupted.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## Why

Your diary will be read years later by somebody who was not there and does not trust it. The words delayed by others tell them nothing they can check. They cannot match them to the allocation sheet, the crane log or the other party's own diary, so the day's loss goes unproven. An entry with the gang, the area, the cause and the hours can be checked against three other records. When they match, the diary becomes the backbone of the claim.

## How do I do it?

1.  Answer five questions in every disrupted entry: which gang, which area, what stopped them, who caused it and for how long.
2.  Use the names and numbers the other records use: the gang leader, the drawing grid, the plant number, the hours on the allocation sheet.
3.  Leave opinion out: write what was seen and said, not who was to blame or what it will cost.
4.  Read the entry back and ask whether a stranger could check it against another record.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) sets up records of activities and resources that can explain what an interruption actually affected.