# My case is strong but the numbers are thin

The events are proved and the case for payment is well argued, but the figures are a spreadsheet nobody in my team fully trusts.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A convincing story can come with round numbers, percentage uplifts and rates nobody can source under pressure. The events may be well documented. But the value still needs quantities, periods, allocations, calculations and a stated basis that someone else can follow.

A strong case with figures nobody can defend still gets paid on the figures. Keep your case on cause and on your right to be paid separate from the money side. Leave unsupported heads visible, rather than folding them into a confident total.

The fix is a sourced schedule. Its workings show what is supported, what is conditional and what the records cannot support.

## What do I need to do?

1.  Index the documents supporting each event in the narrative.
2.  Connect each proposed cost head to its cause, period, resource and calculation.
3.  Reconcile quantities and rates against original records and remove overlaps.
4.  Show unsupported heads and missing evidence separately so the narrative is not mistaken for proof of the amount claimed.

To have this done for you, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)