# Labour is on site and nobody records what it did

Hours are paid, allocation is guessed, and any disruption claim later has nothing underneath it.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Timesheets record hours; payroll and payment records help establish the cost. Without allocation, it can be difficult to show what those hours were spent on. Productivity drops when the gang is moved, the area isn't ready or the work goes out of sequence. The cost lands in the labour account and vanishes there. In the records your business keeps, a paid hour and a productive hour look the same.

Labour allocation fixes that. It means putting each person's hours against an activity and an area, every day. The gap between planned and actual effort can then be measured, not just asserted. A claim backed by allocation sheets traces to activities, hours and notes made at the time.

Without them, separating attributable lost hours from productive work is harder and may require corroborating records. More of the claim then rests on rebuilding events later, which is much harder to prove.

## What do I need to do?

1.  Use a consistent list of activities and areas for daily labour allocation.
2.  Record each person's hours and moves against the work actually performed.
3.  Reconcile sheets with payroll and progress records, correcting discrepancies transparently.
4.  Keep the source records so later productivity or cost assessments can be tested rather than reconstructed from an unsupported estimate.

To have this done for you, see our [Commercial management and cost reporting](<https://www.quantsurv.com/quantity-surveying#client-types>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)