# The other party has taken my figures apart

Their surveyor's response goes through my claim line by line, and some of the hits have landed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

The other party's surveyor has gone through the claim line by line. The response may point to generous quantities, unsupported rates, costs counted twice, or preliminaries shown only as a percentage. Some of those hits will be fair, and some will not.

Answer on instinct and you risk conceding lines the records support, or defending lines they don't. Each point can touch a different amount and need a different source. A sample check is not a full remeasure, and a review finding is not an agreed concession.

The aim is a clear sort of what is supported, what is disputed, what is missing support and what was only sample-checked. Not every challenge can be answered, and nobody should promise it can.

## What do I need to do?

1.  Log each objection, the amount affected, response deadline and person authorised to approve changes.
2.  Separate measurement, arithmetic, entitlement and programme questions.
3.  Answer each point with its calculation and evidence, identifying accepted corrections and information still needed.
4.  Reconcile the item differences to the claim total and retain a versioned record of the response.

To have this done for you, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)