# I've got an extension of time but no money for it

The other party has granted the extension of time, but says the prolongation costs and loss and expense are a separate argument.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

An extension of time gives you more time to finish. On its own, it does not settle whether more money is due, or how it should be worked out. The money still depends on the terms of your contract, the period adopted, the resources actually affected and what has already been paid elsewhere.

The usual shortcut is weeks granted times your tender preliminaries, the site running costs you priced. That may not match how your contract values the cost, or what was actually on site. The cost of running on and the cost of extra resources can fall in the same weeks. But the same cost must never be counted twice. Other causes, the steps you took to limit the cost, and credits all need checking too.

Treat the granted period as a guaranteed payment and the figure is easy to knock down. The job is to set the time decision beside the actual costs, and mark every assumption and specialist input.

## What do I need to do?

1.  Read the separate contractual route for additional cost; an extension of time does not itself establish financial entitlement.
2.  Identify the supported compensable cause and period, which may differ from the extension granted.
3.  Trace affected resources to payroll, invoices and allocation records.
4.  Deduct savings and amounts recovered elsewhere, and explain the calculation rather than multiplying granted weeks by tender preliminaries.

To have this done for you, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service.

For what goes into the cost for the period, see [what to do when you are not sure which prolongation costs you can claim](<https://www.quantsurv.com/delay-and-disruption/problems/building-prolongation>).