# The disruption is real and I can't put a number on it

Everyone knows the sequence was wrecked. Turning that into a disruption claim, with the loss of productivity measured, is the part that keeps failing.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Everyone on the job agrees what happened. The records still cannot show what it cost. Out-of-sequence work, repeated access, stacked trades and changing design all hit productivity. But a total overrun does not show which cause produced which cost, and a total with no cause against it is easy to strike out.

To measure the loss you need a fair comparison. That means a reliable baseline, a clear affected period, and similar activities, outputs and resources. It also means allocation sheets, diaries and daywork records. Test for other causes too, such as weather, supply problems, a change in labour mix or your own changes. If the records are incomplete, another method may suit better, or the result may stay conditional.

One possible method is a measured-mile analysis, set out at paragraph 18.16(a) of the [SCL Delay and Disruption Protocol](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>). It compares your recorded productivity on similar work with and without the disruption. It only works where the records support that comparison. A convenient baseline is not always a reliable one.

The programme, your right to be paid and what legally caused the loss are separate questions. You or the right specialist answer them. Valuing the loss should not turn a factual comparison into an answer on any of them.

## What do I need to do?

1.  Identify the affected activities, output, resource mix and source records.
2.  Choose a method those records can support and test whether the comparison periods and conditions are sufficiently alike.
3.  Calculate the difference with a traceable source for every figure and explain adjustments and other causes.
4.  Separate measured inefficiency from recoverable loss, stating uncertainty where a reliable baseline or causal link is missing.

To have this done for you, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service.

To record the next diversion so it can be costed, see [what to do when the diary says the gang was moved but not where to](<https://www.quantsurv.com/delay-and-disruption/problems/moved-but-not-recorded>).

## Sources

1.  [Delay and Disruption Protocol, 2nd edition, February 2017](<https://www.scl.org.uk/sites/default/files/documents/SCL_Delay_Protocol_2nd_Edition_Final.pdf>). Society of Construction Law.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)