# I know the delay happened, but I can't prove it

The work was stopped and the delay was real, but the paperwork that would show it never got made.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Everyone on site remembers the late handover, the late drawing or the gang standing. But a claim needs evidence that can be found and tested. A programme, photographs nobody can place and people's memories may not show who did what, when, where, or what the event changed.

Your contract, and the evidence, decide what you must show. Emails, delivery tickets, payroll, drawing registers and other firms' logs can help rebuild events. Gaps, contradictions and unknowns stay part of the picture. Label anything rebuilt as rebuilt, and never pass it off as a record made at the time.

The longer it is left, the harder the surviving records are to find. There are two jobs, and they can run together. Save and value what survives for the claim you have, and start a routine for the work still to come. The first assesses and pursues the loss the surviving evidence can support. The second cuts new gaps, though no routine can promise every event will be proved.

## What do I need to do?

1.  Preserve and index the surviving original records.
2.  Separate supported facts, contrary material and unresolved gaps.
3.  Date any new witness recollection when it is written and label it as a later account.
4.  Assess what the evidence can support and request specific missing records without presenting reconstruction as contemporaneous fact.

To have this done for you, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) and [Delay and disruption records setup](<https://www.quantsurv.com/claims#client-types>) services.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)