# Who can put a value on my delay and disruption claim?

A claims consultant or quantity surveyor values it from your records, while a programming expert assesses the time and your solicitor the legal questions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

A claims consultant or quantity surveyor values the monetary claim, using the same event and progress records as any planner or delay expert. Contractual and legal advice establishes the available entitlement where it is disputed. The work must connect three questions: what happened, what recoverable effect it caused and what that effect cost.

An extension of time adjusts the completion obligation. It does not by itself establish a money entitlement or the period of compensable cost. Check the cause, notices and applicable financial route, then reconcile the attributable payroll, hire, allocation and accounting records.

Disruption may be assessed from productivity and resource records without a full critical-path analysis, but programme or sequencing evidence may still be necessary to establish causation and separate other influences. Use the analysis the particular claim requires.

Where supported elements can be assessed separately, develop them while outstanding issues are investigated. Quantsurv's financial claim work is coordinated with the appointed planner and representative, with the scope agreed before work starts.

To have the money side of your claim valued from your records and pursued, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)