Source: https://www.quantsurv.com/delay-and-disruption/faq/what-should-a-diary-say
Content format: Markdown version of the public page.
Content reviewed: 2026-09-25

# What should a site diary actually say?

Record what you saw: who was there, where they worked, what happened, when it started and ended, and what the team did instead.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 25 September 2026 · About 1 min readShare

## The answer

Record what you saw: who was there, where they worked, what happened, when it started and ended, and what the team did instead. Add the output, and a reference to any source such as an email or drawing, where you have one. Keep what you saw separate from what you were told and from what you think caused it. Hours moved to other work are not automatically lost hours. A hold-up in one area does not, by itself, prove delay to completion. So write down the facts on the day, and leave the cost and any effect on completion to be worked out later from the records.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) helps define the daily facts, locations, resources and document references the project needs to record.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)
