# What records help prove delay and disruption?

Keep a site diary, allocation sheets, dated photos, baseline and updated programmes, and a log of instructions, notices, payments and deliveries, set up to suit your contract.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 9 October 2026 · About 2 min readShare

## The answer

Each day, record who was where and what they worked on. Note anything that held the work up, such as no access or missing information. Log labour and plant, and date every photograph. Keep every instruction, change, application, notice, receipt, delivery ticket and off-hire note.

Preserve the baseline, accepted and revised programmes with their submission and acceptance records, contemporaneous progress updates and explanations of changes. Give each record a reference, keep a note of every correction, and link each piece of evidence to where it came from.

Check your contract for the forms it requires, who must sign them and who they go to. Check it too for what triggers a notice, and for any rules on keeping records or holding them for a dispute. How long to keep records can turn on insurance and legal duties, so ask your solicitor rather than assume one period fits all.

Keep the originals. Mark anything written up later, so it is never mistaken for a record made at the time. Review key events as they happen and check the whole set regularly. That regular check does not replace keeping on top of notices day to day.

To have a record routine built into the sheets your site team already fills in, see our [Delay and disruption records setup](<https://www.quantsurv.com/claims#client-types>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)