# We kept almost no records. Is the claim dead?

Not necessarily: a thin file does not settle what the claim is worth or whether it can succeed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Not necessarily: a thin file does not settle what the claim is worth or whether it can succeed. What can still be assessed depends on the evidence you have and on your contract.

Other records may help rebuild events: emails and attachments, delivery tickets, invoices, payroll, allocation data, drawing registers, revision dates and photographs. Logs kept by independent third parties may help too.

Start by keeping everything that survives. Take honest statements of what people remember, dated the day they are written. Work out what each source supports. Label anything rebuilt as a reconstruction. Keep material that goes against you, or leaves questions open, rather than dropping it.

Any missed notice or time limit is a separate question, so get your solicitor's advice on it. For the work still to come, start a proper record routine now, but never rewrite old entries.

Valuing what the surviving records can carry is the first stage of our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service; a routine for the work still to come is set up by [Delay and disruption records setup](<https://www.quantsurv.com/claims#client-types>).