# What does a loss and expense claim look like?

A loss and expense claim is a priced schedule of the extra cost an event caused you, with each head tied to its records.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## The answer

A loss and expense claim is a priced schedule of the extra cost an event caused you, with each head tied to its records. Loss and expense means direct cost you would not have had without the event, such as standing time or extra weeks on site.

A claim that holds up usually has five parts. First comes the event, and the clause in your contract that pays for it. Second is the notice you gave, and when. Third is the affected work and compensable period, supported by the records and any appropriate delay analysis. A granted extension of time does not by itself prove the period recoverable in money.

Fourth are the heads of claim, such as prolongation, disruption, acceleration, head office overheads and financing, each priced on its own. Fifth are the records behind every figure: payroll, hire invoices, allocation sheets and the site diary.

Each head is built from what was actually spent, not from tender allowances or a percentage. Anything already paid in a variation comes off, so nothing is claimed twice. RICS's own guidance on ascertaining loss and expense works the same way, and the other party's surveyor will check each line.

We build the monetary assessment alongside any required programme analysis and advice on entitlement. The recoverable cost period must be linked to a compensable cause and actual attributable loss, rather than taken directly from an extension of time.

### Build your own cost schedule

Reproduce the worked arithmetic in a separate cost schedule built from your own records.

Before including a cost, identify the event, the contractual route, the period and the evidence linking that cost to the event. Record credits and overlap explicitly. Explain missing records and reconstructed figures rather than presenting them as contemporaneous evidence.

To have the claim built and pursued for you, see our [Delay and disruption cost recovery](<https://www.quantsurv.com/claims/delay-and-disruption-cost-recovery>) service.

[Browse delay and disruption in the Library](<https://www.quantsurv.com/library#topic-delay>)

[Browse the Library](<https://www.quantsurv.com/library>)