# Test the payment clauses on a real month before your first application

Payment terms that read well can still fail when you put dates to them, and the first late payment is a bad time to find out. Work every date through for the first month of the job, and settle any conflicts with the other party before the money is due.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Payment terms are often written in pieces: the clause, a schedule of dates, the particulars, and amendments that change one without the others. The result can be a due date before the application, or a final date for payment worked out from a deleted clause. It can also be a notice period nobody can meet. These faults surface in the first month, when a payment is late and nobody can say which date applied. Working the dates through in advance finds them while there is still time to agree the answer.

## How do I do it?

1.  Collect every document that states a payment term: the clause, any schedule of dates, the particulars and the amendments.
2.  Take the first application date on your programme. Work out from the documents the due date, the payment notice date, the pay less notice date and the final date for payment.
3.  Note each conflict, where the documents give different answers or none at all.
4.  Resolve document priority and statutory compliance before agreeing any necessary clarification or amendment in writing.
5.  Put the agreed dates for every month of the programme in the diary.

Our [Signed contract review and action plan](<https://www.quantsurv.com/quantity-surveying#client-types>) checks how the executed payment clauses operate together before dates are used on a live cycle.

[Browse contracts and agreements in the Library](<https://www.quantsurv.com/library#topic-contracts>)

[Browse the Library](<https://www.quantsurv.com/library>)