# Price the terms you cannot change

Every clause that stays in the contract has a cost, paid in cash flow, in risk or in margin, so it belongs in your price. Put a figure on each one you could not get changed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Terms are often treated as the lawyer's part of a contract and the price as the estimator's, and the two never meet. Yet a 60 day payment period ties up working capital every month. Retention held until the whole project completes costs a year or more of financing. Uncapped damages carry a risk your margin was never built to absorb. Where terms remain, assess financing and risk alongside insurance, limits and a decision whether the exposure is acceptable. A price allowance cannot make every risk manageable. Upstream performance or certification conditions also need checking under [Housing Grants, Construction and Regeneration Act 1996, section 110](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>).

## How do I do it?

1.  Take the clauses you asked to change and could not, and the ones you chose not to raise.
2.  Put a financing cost on each payment and retention term: the sum held, for how long, at your cost of borrowing.
3.  Put a risk allowance on each liability term, from a realistic worst case on this programme and how likely it is.
4.  Keep the total as a line of its own in your price build-up, so it is not discounted away in negotiation.

Our [Construction contract review before signing](<https://www.quantsurv.com/quantity-surveying#client-types>) identifies the commercial exposure behind terms that remain in the proposed agreement.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment)](<https://www.legislation.gov.uk/ukpga/1996/53/section/110>). legislation.gov.uk.

[Browse contracts and agreements in the Library](<https://www.quantsurv.com/library#topic-contracts>)

[Browse the Library](<https://www.quantsurv.com/library>)