# Put every notice period and time bar in the diary before work starts

Build a diary from the actual contract’s notices, triggers and deadlines. Give each item an owner and a backup so it can be checked and acted on promptly.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Contracts carry more notices than anyone remembers: for delay, variations, loss and expense, disputed deductions and defects. Amendments often shorten them, or make them conditions of more time or money. Nobody learns the list by reading the contract once at signing. Usually a time bar is found when the first claim is rejected for lateness. A diary set up before work starts records each deadline from the actual contractual trigger, which may precede the date someone logs it.

## How do I do it?

1.  Read the contract and its amendments for every duty to give notice. List each one with its trigger, its period, its form and where it must be sent.
2.  Mark the ones that are conditions of more time or money: they are the time bars.
3.  Record the trigger date and supporting evidence separately from the logging date. Calculate the deadline under the actual clause and set reminders early enough to act.
4.  Name one person to send each kind of notice and one to check it went, in the form and to the address the contract names.
5.  Escalate potential notices immediately; use the weekly comparison with site records as an additional gap check.

Our [Signed contract review and action plan](<https://www.quantsurv.com/quantity-surveying#client-types>) translates the signed terms into a record of triggers, recipients and deadlines.

[Browse contracts and agreements in the Library](<https://www.quantsurv.com/library#topic-contracts>)

[Browse the Library](<https://www.quantsurv.com/library>)