# Ask for the main contract before you sign a back-to-back subcontract

Ask for the main-contract terms your contract incorporates. You need to understand the obligations being passed down before agreeing the price and risk.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

A back-to-back clause makes the main contract part of your deal. That includes its notice periods, delay damages, design and warranty duties and programme. Without a copy you cannot price any of them. Nor can you check whether you have less time to give notice than the other party has itself. The other party has the document and will rely on it when it suits. Asking for it before you sign costs one email. Finding it at the first dispute can leave little time to assess obligations you already accepted.

## How do I do it?

1.  Find the clause that brings in the main contract. Note what it brings in: the whole contract, named parts, or the duties so far as they relate to your work.
2.  Ask in writing for a copy before you sign, offering to accept it with the prices blacked out.
3.  Read the parts that reach your work: notices, programme, delay damages, design, warranties and insurance.
4.  Set each against your contract. Where you get less time or more liability than the other party has, propose wording that brings the two into line.
5.  Record any refusal. Seek disclosure, defined obligations or amendments; if the exposure cannot be assessed or accepted, consider declining the work rather than assuming a price allowance solves it.

Our [Construction contract review before signing](<https://www.quantsurv.com/quantity-surveying#client-types>) identifies incorporated obligations and missing documents before you accept risks from another agreement.

[Browse contracts and agreements in the Library](<https://www.quantsurv.com/library#topic-contracts>)

[Browse the Library](<https://www.quantsurv.com/library>)