# The payment dates in the contract I've signed don't add up

We have signed, and the payment clause, the schedule of dates and an amendment each give a different due date.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Payment terms come from several places: the clause itself, a schedule of dates, the particulars and any amendments. When each is written separately, they can disagree. One can set a due date before the application. Another can fix the final date for payment by a clause the amendments deleted. A notice period may be impossible to meet on the dates given.

This is not a detail. The dates decide when the other party must send a payment notice. They also set the deadline for a pay less notice, the notice it must send if it plans to pay you less than it said. They help establish the payment timetable. Whether an application establishes the notified sum depends on the applicable notice mechanism, and suspension has separate statutory or contractual conditions. If nobody knows the dates, nobody on either side knows when those rights arise.

If the payment terms in a construction contract are inadequate, [the Housing Grants, Construction and Regeneration Act 1996](<https://www.legislation.gov.uk/ukpga/1996/53/part/II>) can replace them. The replacement terms come from [Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II>). Which terms govern your contract is a question for your solicitor. Working out which dates the paper actually gives, and where they conflict, is not.

## What do I need to do?

1.  Collect every payment clause, schedule and amendment and record the document priority provisions.
2.  Map an actual payment cycle, keeping the application, due date, notice deadlines and final date separate.
3.  Identify conflicts and obtain advice on interpretation or compliance before agreeing corrections.
4.  Keep the written clarification and assign responsibility for each live deadline while the issue is unresolved.

To have this done for you, see our [Signed contract review and action plan](<https://www.quantsurv.com/quantity-surveying#client-types>) service.

## Sources

1.  [Housing Grants, Construction and Regeneration Act 1996, Part II (Construction contracts), as amended by the Local Democracy, Economic Development and Construction Act 2009, Part 8](<https://www.legislation.gov.uk/ukpga/1996/53/part/II>). legislation.gov.uk.
2.  [Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II (Payment)](<https://www.legislation.gov.uk/uksi/1998/649/schedule/part/II>). legislation.gov.uk.

[Browse contracts and agreements in the Library](<https://www.quantsurv.com/library#topic-contracts>)

[Browse the Library](<https://www.quantsurv.com/library>)