# The subcontract binds me to a main contract I've never seen

The subcontract says we take on the main contractor's duties to its client for our work, and nobody has sent us the main contract.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A back-to-back subcontract passes the main contract's terms down to you. It usually does this with a clause saying you are bound by the main contract so far as it relates to your work. Many add that you must not put the other party in breach of it. The main contract then becomes part of your deal, often without a copy ever reaching you.

The terms that come down this way are the ones you cannot price without seeing them. They include the notice periods, the delay damages the client can charge, the design and warranty duties, and the programme. The other party will want notices from you sooner than its client wants them from it. So a 14 day notice period in the main contract can leave you 5 days in the subcontract.

Whether a general clause like this brings in every term of the main contract, or only some, depends on its wording. That is a question for your solicitor. The commercial risk is plain: sign without reading the main contract, and you may have agreed to terms you never priced.

## What do I need to do?

1.  Request the main-contract terms and other documents incorporated into your subcontract.
2.  Map the obligations passed down to you, including notice periods, payment conditions, design duties and liability.
3.  Record anything withheld or unclear and seek a written clarification, exclusion or limit before committing.
4.  Check the final agreement against the documents reviewed. Do not treat an unseen obligation as a priced or understood risk.

To have this set up for you, see our [Construction contract review before signing](<https://www.quantsurv.com/quantity-surveying#client-types>) service.

[Browse contracts and agreements in the Library](<https://www.quantsurv.com/library#topic-contracts>)

[Browse the Library](<https://www.quantsurv.com/library>)