# They've rejected my claim under a time bar I didn't know I'd signed

We notified a delay 3 weeks after it started, and the other party has rejected it under an amendment that gave us 7 days.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

Amendments often turn a notice clause into a time bar. A time bar says you must give notice within a set number of days, in a set form, or lose your right to more time or money. The clause is signed along with everything else. Nobody on site learns it exists until the other party rejects the first claim under it.

Whether your notice was really late, and what follows if it was, depends on three things. They are the exact wording, when the period started, and what the other party has said and done since. Those are questions for your solicitor, so ask before you accept the rejection.

What is certain is that the same clause applies to every event still to come on this job. So do the other notices in the contract. Miss the next deadline and you can lose that claim too. That deadline is the one you can still prevent.

## What do I need to do?

1.  Preserve the rejection, clause, notice and proof of service. Ask your solicitor promptly about the disputed time bar.
2.  Record the event and awareness dates with their supporting evidence. Do not backdate a notice or invent a trigger.
3.  Identify every remaining notice requirement, recipient, permitted method and deadline from the actual contract.
4.  Give each deadline an owner and backup, and retain evidence of notices issued.

To have this done for you, see our [Signed contract review and action plan](<https://www.quantsurv.com/quantity-surveying#client-types>) service.