# Should I sign my contract as a deed?

Have the effect checked before signing. In England and Wales, many simple-contract claims have a 6-year limitation period and claims on a deed 12 years, but the claim, start date and exceptions matter.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## The answer

Have the effect checked before signing. In England and Wales, many simple-contract claims have a 6-year limitation period and claims on a deed 12 years, but the claim, start date and exceptions matter. The general rules appear in [section 5 of the Limitation Act 1980](<https://www.legislation.gov.uk/ukpga/1980/58/section/5>) and [section 8](<https://www.legislation.gov.uk/ukpga/1980/58/section/8>). Do not simply count from the signing date or assume all defects and payment claims start together.

Ask your solicitor about execution, limitation, contractual limits and any special statutory claims relevant to the work. Check the effect with your insurer and agree a suitable records-retention policy. If a deed is requested, understand the additional exposure and any proposed changes before accepting it.

To have the deed, and every other term that moves risk onto you, rated and priced before you sign, see our [Construction contract review before signing](<https://www.quantsurv.com/quantity-surveying#client-types>) service.

## Sources

1.  [Limitation Act 1980, s 5 (Time limit for actions founded on simple contract)](<https://www.legislation.gov.uk/ukpga/1980/58/section/5>). legislation.gov.uk.
2.  [Limitation Act 1980, s 8 (Time limit for actions on a specialty)](<https://www.legislation.gov.uk/ukpga/1980/58/section/8>). legislation.gov.uk.