# What is a main contractor's discount, and should I agree to it?

A main contractor's discount is a percentage taken off every payment to you, so agree to it only if it is already in your price.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

A main contractor's discount is a percentage taken off every payment to you, so agree to it only if it is already in your price. It is often written as MCD, or as a cash discount, and is often 2.5 per cent.

It began as a discount for paying on time. Some contracts still allow it only when you are paid by the final date for payment. Others take it from every payment, however late. Read the clause to see which you have. Where the discount depends on paying on time, it should not be taken from a late payment.

Before you sign, ask for the discount to be removed, or limited to payments made on time. If it stays, add it to your price. To keep your net price after a 2.5 per cent discount, add one thirty-ninth to it. Taking 2.5 per cent off the higher figure brings you back to your price.

To have the discount and every other deduction in the contract found and priced before you sign, see our [Construction contract review before signing](<https://www.quantsurv.com/quantity-surveying#client-types>) service.