Source: https://www.quantsurv.com/contra-charges/tips/sign-off-finished-areas
Content format: Markdown version of the public page.
Content reviewed: 2026-10-10

# Get finished areas signed off before the next trade moves in

Seek a dated handover record and photographs of completed areas. These help establish condition and later access, without conclusively deciding who caused subsequent damage.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

Once you finish an area, other trades follow: electricians chasing walls, decorators, floor layers, the client's fit-out. Damage found at snagging gets charged to the trade whose work is damaged, or to the last trade the site manager links with it. Responsibility depends on the evidence and contractual risk allocation; damage to your work does not by itself prove that you caused it. A signed handover and dated photographs fix the state of the area on the day you left it. They take 10 minutes, and they turn an argument about memory into a comparison of two dated records.

## How do I do it?

1.  Walk each finished area with the other party's site manager, and record its condition on a one-page handover sheet.
2.  Take dated photographs from fixed positions, wide shot first, and file them with the sheet the same day.
3.  Ask the site manager to sign the sheet. If they will not, email them that day saying the area was handed over, with the photographs attached.
4.  Keep the sheets in one folder by area, so you can check any damage charge against the handover in minutes.

Our [Construction contract management](<https://www.quantsurv.com/quantity-surveying#client-types>) records condition and handover before later trades alter the evidence of completed work.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)
