# They've charged me for defects I was never asked to fix

Another contractor has put right work it says was defective, and the bill has come off our account without anyone telling us first.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

The first you hear of the defect is the deduction. The other party has brought in another contractor, the work is done, and its invoice has come off your payment. Check any notice and opportunity-to-remedy requirement, the actual defect and responsibility for it. Urgency, the contract wording and the facts can affect whether another contractor could properly be engaged.

Left unchallenged, you pay whatever the other contractor charged, sometimes for work that was never yours. The questions that decide it are simple. Was a notice to remedy given, and when, and to whom? Was the work defective, and was it yours at all? And what should the repair have cost? Test the recoverable cost under the contract and applicable loss principles, including scope, reasonableness, urgency and mitigation; your own hypothetical repair cost is not an automatic ceiling.

## What do I need to do?

1.  Request the alleged defect, notice to remedy, repair instructions, invoices and day sheets.
2.  Compare them with your scope, handover records and any opportunity to inspect or rectify.
3.  Check the necessary work and reasonable cost, supporting any alternative estimate.
4.  Obtain advice on disputed notice effects and respond item by item; a missing invitation does not automatically defeat the charge.

To have this done for you, see our [Contra-charge review and challenge](<https://www.quantsurv.com/claims/contra-charge-review-and-challenge>) and [Contra-charge prevention process setup](<https://www.quantsurv.com/claims#client-types>) services.