# Can they set off contra-charges against my final account?

Yes, but only where each charge has a proper basis, in your contract or in law, and an amount the evidence supports.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## The answer

Set-off means the other party taking a sum it says you owe out of the sum it owes you. A contra-charge is one particular cost it puts forward, such as making good, attendance or delay. For each item, check your contract, what caused the cost, the records and the amount.

Check the notices for the final payment as a separate point. A notice problem may affect that payment without deciding who is right in the end. A charge that first appears at final account is not proved or defeated by its timing alone. So keep the schedule, and answer each line rather than accepting or rejecting the total.

Our [Contra-charge review and challenge](<https://www.quantsurv.com/claims/contra-charge-review-and-challenge>) service answers deductions you have received.

[Browse payment and deductions in the Library](<https://www.quantsurv.com/library#topic-payment>)

[Browse the Library](<https://www.quantsurv.com/library>)