# Do they have to let me fix a defect before charging me for it?

Usually, yes: most contracts say you must get notice and a reasonable chance to fix it before others are brought in at your cost.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

Usually, yes: most contracts say you must get notice and a reasonable chance to fix it before others are brought in at your cost. It depends on your own contract, so read its defects and set-off clauses rather than assuming. Amended forms sometimes shorten the period, or let the other party act at once in an emergency.

If your contract requires notice and none was given, the charge is exposed. If some cost is recoverable, examine the actual notice and remedy terms, urgency, mitigation and reasonable loss. Your evidenced cost of repair can inform the challenge, but it is not an automatic legal cap on the other party's recovery.

If a notice was given and you did not respond, your position is much weaker. Whether a missed notice defeats the charge entirely, or only reduces it, can be a legal question for your solicitor. Either way, answer every notice to remedy in writing, with a date.

Keeping every notice to remedy answered in writing is part of our [Contra-charge prevention process setup](<https://www.quantsurv.com/claims#client-types>) routine.