# Record when you became aware of the event

Record the event and when you became aware of it. Then check the notification period, trigger and exceptions in your actual NEC contract.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 1 min readShare

## Why

A period quoted for an ECC main contract must not be copied into an ECS subcontract. Amendments can also change the rule. Evidence of awareness helps establish the starting point; it does not decide every time-bar question.

## How do I do it?

1.  Keep the dated instruction, site record or email that first identified the event.
2.  Check the actual form, edition, amendments and notification clause.
3.  Notify using that procedure promptly, and obtain advice if the timing is uncertain.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) records the event chronology and the evidence behind the notification trigger.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)