# Diarise the quotation period the day you are asked to quote

Once the other party asks you to quote, verify the communication or receipt trigger from which the quotation period runs. It is 3 weeks in the unamended NEC4 main contract, and whatever your contract sets. Put the date in the diary the day the instruction arrives, and if you need longer, agree an extension before the period ends. A quotation that misses its period lets the other side make its own assessment.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

The quotation period is short, and it starts on a day nobody on site notices: the day the instruction to quote arrives, usually one email among twenty. The team treats it like a variation price, to send when the cost is known, and the period passes. The contract then lets the other party make its own assessment, and the side paying for the event rarely assesses it generously. Seek an extension early and verify the agreement requirements in the actual clause; do not rely on an unanswered request. The defence is a diary date set the day the instruction lands, and an early decision on whether the period is long enough.

## How do I do it?

1.  Log every instruction to quote the day it arrives, with the date received and the period your contract gives.
2.  Put the submission date in the diary, with a checkpoint halfway through to decide whether the quotation can be finished in time.
3.  Write to agree an extension before the period ends if the quotation cannot be finished, giving the reason and your proposed new date. Put the agreed date in the diary.
4.  Diary the reply period from its actual contractual trigger, with evidence of communication or receipt and any agreed extension.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) tracks quotation requests, agreed extensions and responses against the actual NEC contract.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)