# Answer a refusal on the ground it gives

When the other party says an event is not a compensation event, find the ground it relies on and check your contract allows it. Then answer that ground with the records that meet it, in writing, through the contract's communication system. Put any period for raising a disagreement in the diary. A one-line refusal nobody answers tends to become the position.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## Why

A refusal usually arrives as one line, and one line is easy to file and forget. The final account then starts from it. But the contract only lets the other party refuse on the grounds it lists, and each ground is met by different evidence. Fault is met by the Accepted Programme and the site records. A no-effect ground must be tested against all relevant cost, Completion and Key Date effects. Not listed is met by the clause wording and your amendments. An answer aimed at the ground given, with those records attached, has to be dealt with. A general complaint that the refusal is unfair gives it nothing to answer.

## How do I do it?

1.  Log the reply the day it arrives, with its date and the ground it gives in its own words.
2.  Read that ground against the grounds your contract allows. Say so plainly where the reply gives no ground, or one the contract does not list.
3.  Gather the records that meet the ground given. Use the Accepted Programme and the diary for fault, and both cost and programme evidence for an alleged absence of effect. Use the clause and amendment schedule for an event said not to be listed.
4.  Read your contract's dispute clause for any period within which a disagreement must be raised, and put it in the diary from the date of the reply.
5.  Send the answer through the contract's communication system, asking for the event to be accepted and a quotation instructed, and put the reply period in the diary.

Our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) addresses the stated reason for refusal using the event, clause and supporting records.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)