# They say it isn't a compensation event

We notified the event in time, and the reply came back that it is not a compensation event, with no quotation instructed.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

The other party's reply to a notification can decide an event before any money is discussed. The contract only lets it refuse on the grounds it lists. Examples are that the event came from your own fault, had no effect on cost or time, or is not one of the compensation events the contract names.

Each ground is tested differently. A fault argument turns on the Accepted Programme and the records of what happened. A no-effect argument needs the cost and relevant time effects checked. A not-listed argument turns on the exact wording of the clause and your amendments. A reply with an unsupported ground may need a formal challenge. Do not treat a flawed rejection as silence without checking the actual procedure.

The reply often arrives as a single line, and a single line is easy to accept by default. Leave it unanswered and the event can reach the final account at nil.

## What do I need to do?

1.  Read the rejection against the event provisions and amendments in your contract.
2.  Identify the event relied on and assemble the instruction, programme, diary and cost records supporting it.
3.  Respond to the actual ground given, within any applicable period.
4.  Keep the rejection and response together and obtain advice before pursuing a contested entitlement or treating silence as acceptance.

To have this done for you, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) and [NEC compensation-event process setup](<https://www.quantsurv.com/claims#client-types>) services.