# We notified the compensation event and heard nothing back

The notification went in weeks ago, no reply has come, and the event is sitting unimplemented.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

A notification with no reply feels like an open question, so it gets left open. The event sits on the log as notified, nobody quotes, and it drifts towards the final account.

The compensation event procedure gives the other party a period to reply. The relevant form may allow a notice of failure to reply. If the silence then carries on for the further period the contract gives, the event is treated as accepted and a quotation as instructed. Your amendments may change those periods or that step, so read them first.

Waiting for the silence to end costs you, not the other party. An available notice-of-failure mechanism may require you to act before its further period starts; identify that step instead of relying on silence alone. By the time anyone asks about the event, the records behind its cost have gone cold.

## What do I need to do?

1.  Check the reply period and establish when the original notification was validly served.
2.  Read the contract's failure-to-reply procedure before assuming acceptance.
3.  Serve any required reminder correctly and record the further period and service evidence.
4.  Confirm the resulting position under the actual terms before preparing the next submission or relying on a deemed consequence.

To have this done for you, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) and [NEC compensation-event process setup](<https://www.quantsurv.com/claims#client-types>) services.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)