# They've made their own assessment and it's far too low

We sent the quotation, and instead of accepting it the other party assessed the event itself, at a fraction of what it cost.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 11 October 2026 · About 2 min readShare

## What does this mean for me?

NEC only lets the other party make its own assessment of an event in limited cases. It can do so where no quotation arrived in time, or where it decides your quotation was wrong and does not ask for a revised one. It can also do so after a programme failure the contract names. A notified assessment may implement the change under the contract without your agreement. Check implementation, any express correction mechanism and the applicable dispute route rather than assuming a replacement quotation will reopen it.

Compare the assessment with your quotation: people and hours, equipment duration, forecast work, cost eligibility and Fee. Ask for the basis of any unexplained difference rather than assuming every reduction is wrong.

Each cut can be tested against the applicable cost schedule or permitted valuation basis, and your records. But resending the original quotation tests nothing, unless you explain the disputed components and follow the applicable challenge route.

## What do I need to do?

1.  Compare the assessment line by line with the contractual cost rules and your quotation.
2.  Trace disputed hours, equipment, quantities, forecasts and Fee to their records.
3.  Separate supported corrections from fair reductions and identify any required programme input.
4.  Submit a reasoned response and assess the next contractual or dispute step with your adviser if agreement remains out of reach.

To have this done for you, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) and [NEC compensation-event process setup](<https://www.quantsurv.com/claims#client-types>) services.