# What should an NEC compensation event quotation contain?

Three things: the change to your price built from Defined Cost plus the Fee, any delay shown on a revised programme, and your assumptions.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 7 October 2026 · About 2 min readShare

## The answer

Three things: the change to your price built from Defined Cost plus the Fee, any delay shown on a revised programme, and your assumptions. The contract names all three.

First, the change to the price. Under NEC4 that is the event's effect on Defined Cost plus the Fee. Defined Cost is the contract's own measure of cost, and the Fee is the amount calculated using the applicable fee percentage. Separate actual and forecast Defined Cost at the applicable dividing date, not simply the quotation's submission date. Use the relevant Schedule or Short Schedule of Cost Components, or any permitted agreed alternative, with the correct Fee treatment.

Second, any delay to the completion date or a key date. Show it on a revised programme, rather than just stating it.

Third, the assumptions. Where the other side stated assumptions when it asked you to quote, base the quotation on them and say so. Where you had to make your own, list them. Distinguish an assumption expressly stated through the contractual assessment mechanism from your own estimating assumption. Listing your own assumption does not automatically create a later correction right.

Add a cover sheet with the event, the notification date, the instruction date and the total, so the reader sees the shape before the detail.

### Assemble the quotation package

Use your cost schedule for the cost build-up. Confirm the form, edition, option and amendments before choosing cost components or Fee percentages.

Keep the event notification, quotation request, assessment date, cost evidence and programme assessment together. State assumptions, exclusions and any risk allowance. The worksheet total covers cost only; it does not calculate effects on completion or replace the submission required by your contract.

For the clause timetable, revised quotations and deemed acceptance, see [how NEC4 clause 62 works](<https://www.quantsurv.com/compensation-events/faq/nec4-clause-62-quotations-for-compensation-events>).

If this is your first quotation and the period is running, see [what to do when the compensation event quotation has to go in and you've never built one](<https://www.quantsurv.com/compensation-events/problems/first-ce-quotation>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) prepares a traceable cost build-up, assumptions and supporting records for an agreed quotation scope.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)