# What does the Fee mean under NEC4?

The Fee is an amount calculated by applying the contractual fee percentage to Defined Cost. The percentage and the resulting Fee are different figures.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 10 October 2026 · About 2 min readShare

## The answer

The Fee is an amount calculated by applying the contractual fee percentage to Defined Cost. The percentage and the resulting Fee are different figures. Read the definition and percentage in your own contract, including amendments; NEC3 arrangements should not be assumed to match NEC4.

First establish the applicable [Defined Cost](<https://www.quantsurv.com/compensation-events/faq/what-does-defined-cost-mean-under-nec4>). Then apply the relevant percentage to that base. Check which costs are already covered by a component or by the Fee before adding supervision, design, overheads or profit. A person's head-office location alone is not a complete test of whether their work falls within a permitted component.

For a compensation event, keep cost, risk allowances, savings and Fee identifiable. An omission or other reduction needs the contract's assessment rules; do not deduct an arbitrary percentage from the whole contract price. Under target options, changes to the target and assessment of routine payment also need to be kept distinct. Use your cost schedule to show the calculation and preserve your assumptions.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) shows the applicable Fee and its calculation separately from the Defined Cost build-up.