# How does NEC4 ECC clause 64 work?

The other party’s assessment must be checked against its contractual grounds and assessment rules.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

If the other party makes its own compensation event assessment, identify the provision permitting that action under your executed contract and why it says the trigger occurred. NEC4 ECC clause 64 provides main-contract context; its Project Manager role should not be substituted into your contract without checking the actual wording.

Request the assessment and workings. Compare the event scope, omitted-work credits, dividing date, applicable cost schedule, Fee, assumptions and programme inputs. Bill rates are not automatically wrong: establish whether the contract or a valid agreement permits rates, lump sums or another alternative basis for this assessment.

Prepare a reconciliation showing the difference on each disputed input and the supporting evidence. A missed quotation deadline or disagreement with your original submission does not make every figure in the other assessment correct. Follow the actual response or dispute procedure and obtain advice on any deadline or procedural consequence.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) organises the quantities, cost evidence and assumptions needed to review the assessment. For a contested position: Our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) tests the assessment against the applicable contract rules and supporting records.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)