# How does NEC4 ECC clause 62 work?

Prepare the quotation to your own NEC contract's content and timetable, keeping cost, programme effects and assumptions traceable.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

The quotation stage turns a notified event into a proposed assessment of its effect. Start with the executed NEC form, main option, amendments and instruction to quote. Record the submission period, valid recipient, reply period and any agreed extension. Do not copy ECC main-contract periods into an ECS or short subcontract.

Show the event baseline and the changed work, the applicable Defined Cost or permitted alternative valuation basis, Fee and the actual/forecast split at the relevant dividing date. Explain credits, mitigation and the programme effect. Distinguish your estimating assumptions from assumptions formally stated under the contract, because their correction may have different consequences.

If more information is needed, seek an agreed extension before the deadline and keep evidence of it. For a revised quotation, answer the reasons given and identify what changed. If the reply is overdue, use the actual reminder or notice-of-failure mechanism; silence at the first deadline does not universally accept your figure.

### Keep a clear submission record

Prepare the cost build-up using your cost schedule, then attach the relevant programme changes and assumptions. Identify the version submitted, its date and the required recipient.

Keep proof of service and a record of each response. A spreadsheet saved on your computer is not evidence that a quotation reached the contractual recipient.

For a plain checklist of the three parts, see [what an NEC compensation event quotation should contain](<https://www.quantsurv.com/compensation-events/faq/what-should-a-compensation-event-quotation-contain>).

For the dates worked through on an example, see [how long the contractor has to submit a compensation event quotation](<https://www.quantsurv.com/compensation-events/faq/how-long-to-submit-a-compensation-event-quotation>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) prepares the quotation from the requested scope, cost basis and stated assumptions. For a contested position: Our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) checks a rejected or reduced quotation against clause 62.2 and the cost records.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)