# How does NEC4 ECC clause 61.4 work?

A decision on a notified event must be tested against the actual contract’s permitted grounds.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

When you receive a decision on a notified compensation event, compare the reason given with the grounds permitted by the executed contract. NEC4 ECC clause 61.4 concerns the Project Manager under the main contract; identify the corresponding provision and authorised decision-maker under your own contract.

A reasoned rejection and no response need different actions. For a rejection, identify the exact ground, the disputed facts and the supporting records. Answer that issue instead of simply resending the notification or increasing the quotation. Preserve any dispute deadline.

For silence, verify valid service, the actual response period and any agreed extension. Check whether the applicable clause requires a notice of failure followed by a further period, and serve it correctly before relying on its consequences. Acceptance that an event is a compensation event is not necessarily acceptance of a particular price or completion change.

For deemed acceptance at every stage, with the dates worked through, see [whether a compensation event is deemed accepted if nobody replies](<https://www.quantsurv.com/compensation-events/faq/deemed-acceptance>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) tracks the decision and any follow-up procedure against the actual response periods. For a contested position: Our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) reviews the decision and supporting records against the applicable contract procedure.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)