# How does NEC4 ECC clause 61.3 work?

Use the notification period, trigger and exceptions in the actual NEC contract.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

Use the notification period, trigger and exceptions in the actual NEC contract. The commonly cited eight-week ECC period differs from the seven-week ECS period, and amendments can change either; preserve the event, awareness and valid-service evidence. These clause numbers refer to NEC4 ECC guidance; apply the corresponding provisions of your actual contract rather than substituting parties into the main contract. Record the operative form, amendments, notice requirements and service evidence. We prepare the cost records and assessment; your representative deals with contractual interpretation and dispute procedure, and your appointed planner supplies any required delay analysis.

### Check the notification before pricing

Record the event, when it became apparent, the relevant instruction and the notification sent. Read the actual form and amendments before calculating any deadline.

Keep the notification process separate from the later quotation worksheet. An early warning, meeting note or price submission should not be assumed to perform another contractual communication automatically.

If the eight weeks may already have passed, see [what happens if you miss the 8 week deadline for a compensation event](<https://www.quantsurv.com/compensation-events/faq/miss-the-eight-week-deadline>).

For what a notification should say and how to send it, see [how to notify a compensation event under NEC4](<https://www.quantsurv.com/compensation-events/faq/notify-a-compensation-event>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) records awareness, responsibility and notification requirements against the signed terms.