# What does NEC4 ECC clause 60.1 mean?

An NEC compensation event must fit the events and conditions in the actual contract.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

An NEC compensation event must fit the events and conditions in your actual contract. Clause 60.1 is a starting list, not necessarily the whole list: selected options, additional events in the Contract Data and amendments may add or alter triggers. The familiar numbered list comes from NEC4 ECC; use the corresponding wording and roles in your actual NEC form.

Identify the obligation or instruction first. Compare it with the agreed Scope, required dates and risk allocation, then record the particular event relied on. An overrun, low margin or unexpected cost alone is not a compensation event. Keep any early warning distinct from the event notification and protect the actual notification deadline.

If a quotation is instructed, assess the change using the applicable cost rules, dividing date and Fee, with any Completion or Key Date effect supported separately. Track acceptance, assessment and implementation as distinct stages. An event log should show the next action, responsible person and deadline as well as the proposed value.

For a plain-English overview across NEC forms and amendments, see [what a compensation event is](<https://www.quantsurv.com/compensation-events/faq/compensation-event>).

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) checks the listed event and amendments before the notification and assessment procedure is followed. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)