# What does NEC4 ECC clause 60.1(9) mean?

Withholding acceptance for a reason outside the permitted grounds can support a compensation event under the relevant terms.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

Withholding acceptance for a reason outside the contractual grounds may support a compensation event. The ECC clause 60.1(9) reference must be checked against the acceptance provision and roles in your own contract.

Start with a complete submission that actually required acceptance. Retain the information supplied, date, communication record and refusal. Identify the exact ground given and compare it with the permitted grounds, including any relevant qualification or amendment. Disagreement with the outcome alone does not establish a compensable refusal.

Answer the stated reason with evidence and follow the required notification and challenge route. If delay or replacement procurement follows, separate the cost attributable to an unjustified refusal from deficiencies in your own submission and other causes. Do not proceed as though acceptance was granted merely because you dispute the reason.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) checks the reason given against the applicable acceptance provisions before preparing the event record. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.