# What does NEC4 ECC clause 60.1(6) mean?

A missing contractual reply may support a compensation event if the applicable conditions are met.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 1 min readShare

## The answer

A late reply can support a compensation event where the actual contract required that reply and the event conditions are met. The ECC clause 60.1(6) reference should be mapped to your contract's roles and communication provisions. An email asking for general help is not necessarily a communication carrying a contractual reply period.

Keep the complete submission, evidence of valid communication, the applicable period and the actual reply. Check whether the period was extended or the submission required correction. Identify what procurement, design or site activity depended on the reply and what could continue meanwhile.

A late-reply compensation event is distinct from a notice-of-failure or deemed-acceptance mechanism. Follow each relevant procedure separately; neither a chase email nor the passage of time automatically establishes acceptance. Assess the additional effect caused by the late response, not the whole value of the submitted design.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) records the communication, reply date and consequences of any late response.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)