# What does NEC4 ECC clause 60.1(5) mean?

Interference by others may support a compensation event under the relevant programme or Scope obligations.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 1 min readShare

## The answer

Interference by another party may support a compensation event where the actual contract's programme or Scope obligations are breached. ECC clause 60.1(5) uses main-contract roles; identify who the relevant party is under your contract and what it was required to do or avoid.

Another trade being present is not enough on its own. Record the expected clearance, access or sequence, the affected workface and the actual interference. Distinguish unavoidable shared working already allowed for from a departure from the stated arrangement.

Check available alternatives, mitigation and any revised instruction. The assessment should show how the interference affected productivity, resources or programme, with the cost split and required notification evidence. Avoid charging the same hours as both standing time and disruption.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) compares the actual interface with the working assumptions stated in the contract and programme.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)