# What does NEC4 ECC clause 60.1(4) mean?

An instruction to stop or defer work can support a compensation event, subject to the actual terms and responsibility for the event.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

An authorised instruction to stop or defer work can support a compensation event under the applicable contract, subject to its conditions and responsibility provisions. The ECC clause 60.1(4) description is not a substitute for the corresponding contract instruction and event clauses.

Keep the instruction, affected area and activities, the reason given and the authorised restart. Check whether some obligations or areas continued. Confirm unclear oral directions promptly while protecting any separate notice deadline.

Record which resources had to remain, which could be redeployed and what demobilisation or remobilisation was necessary. Assess time separately using the relevant programme: elapsed stoppage is not automatically the change to Completion. If the stop arose from your own failure, identify the actual contractual consequence rather than assuming every stop instruction is compensable.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) records the stop instruction, affected work, resource consequences and subsequent restart information. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)