# What does NEC4 ECC clause 60.1(21) mean?

An additional compensation event depends on the wording incorporated into your contract, including any conditions attached to its trigger.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

NEC forms can provide for additional compensation events identified in the Contract Data or amendments. If you are working under a subcontract, establish that the additional event forms part of your own agreement; an event added to the main contract does not automatically flow into the subcontract.

Read the whole trigger. It may name a particular obligation, person, date, location or programme and may contain qualifications. Save the incorporated wording and the evidence showing whether each condition happened. Then follow the notification, quotation and assessment procedure applicable to that event, including any exceptions or amendments.

The additional event establishes a possible contractual route. Its occurrence does not automatically establish the amount of extra cost or an equal extension of time. Assess the effect using the applicable cost rules, programme and mitigation records, and separate overlapping recovery under another event.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) checks the additional events actually included in the Contract Data and amendments. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)

[Browse the Library](<https://www.quantsurv.com/library>)