# What does NEC4 ECC clause 60.1(20) mean?

A rejected proposal may support recovery of eligible quotation-preparation costs under the applicable NEC provision, rather than payment for the proposed work.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 1 min readShare

## The answer

First check whether your actual NEC contract includes the corresponding compensation event and which person can request the quotation. ECC clause 60.1(20) is main-contract context; its wording and numbering do not by themselves establish your contract entitlement.

Keep the request for a proposed instruction separate from an instruction to carry out the work. Record the proposal, quotation submitted and decision not to accept it. Check what the provision allows for preparation and whether any separate agreement covered design, surveys or supplier charges. A quotation request does not automatically authorise construction or purchase of the proposed equipment.

Build the assessment from eligible preparation records and the applicable cost schedule or agreed basis. Separate work already required by your original scope, speculative expenditure and costs of work never instructed. Apply Fee only as the contract permits.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) keeps the instruction to quote, preparation records and decision together for the applicable assessment.

[Browse changes and extra costs in the Library](<https://www.quantsurv.com/library#topic-changes>)