# What does NEC4 ECC clause 60.1(14) mean?

An event allocated to the other party’s liability may support a compensation event under the actual terms.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

An event allocated to the other party's liability can support a compensation event where your actual contract provides for it. ECC clause 60.1(14) refers to the Client's liabilities in that contract; the end client is not automatically the relevant contracting party for your contract.

Read the liability allocation, care-of-the-works and insurance provisions together. Identify the event, who caused it, the affected property and the period of responsibility. An insurance obligation and legal liability are related but distinct questions.

Preserve dated condition records and the incident evidence before repairs. Define the necessary repair scope and assess eligible net cost and programme effects, allowing for salvage, betterment where relevant and any insurance or other recovery. Do not claim the same loss twice.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) separates the relevant allocation of liability from the event valuation and supporting costs. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.