# What does NEC4 ECC clause 60.1(12) mean?

Unexpected physical conditions can support a compensation event where the contractual foreseeability test is satisfied.

by [Jack Butler-Kettle](<https://www.quantsurv.com/about#jack-butler-kettle>), MCIArb, NEC Registered Adjudicator · Last reviewed 14 October 2026 · About 2 min readShare

## The answer

Unexpected physical conditions may support a compensation event only where the actual contractual test is met. ECC clause 60.1(12) asks what an experienced contractor would have assessed at the relevant Contract Date. Something being unexpected to you is not enough. The assessment must use the contractual probability threshold and the information the contract requires you to consider. Check the corresponding contract wording and amendments.

Preserve Site Information, surveys, tender information, available observations and the discovery location and condition. Identify what an experienced contractor should reasonably have allowed for under the actual test, rather than using your estimate alone as the baseline. Weather follows a separate provision.

Record the work needed because of the qualifying difference and keep ordinary excavation or other base work separate. Give the required notice promptly, preserve evidence before the condition is disturbed where practicable and coordinate the cost and programme assessment. An unrecorded obstruction is relevant evidence, not an automatic entitlement.

Our [Variations and compensation events](<https://www.quantsurv.com/quantity-surveying#client-types>) organises the physical-condition evidence and contract information needed for the assessment. For a contested position: To have a refused event tested against the clause it falls under and pressed to implementation, see our [NEC compensation event recovery](<https://www.quantsurv.com/claims/nec-compensation-event-recovery>) service.